Portfolio of Upcoming Power Generation Projects
As on March 13, 2025
Sr.# |
Project |
Sponsor/ Company Name |
Location |
Fuel |
Capacity |
Expected COD/Remarks |
2025 |
||||||
1 |
Shah Taj Sugar Mills Project |
Shah Taj Sugar Mills |
Mandi Baha-ud-Din, Punjab |
Bagasse |
32 |
Apr-25
(Under Construction) |
Sub Total (2025) |
32 |
|
||||
2026 |
||||||
2 |
Riali-II |
Riali Hydro Power Co. |
Ghori Wala Nullah, Muzaffarabad AJ&K |
Hydel |
7.08 |
Dec-26
TLOS issued (Under Construction) |
3 |
Zorlu Solar Pakistan Ltd |
Zorlu Enerji, Turkiye |
QASP, Bahawalpur, Punjab |
Solar |
100 |
Dec-26 TLOS issued. Decision on Tariff Petition is awaited from NEPRA. |
Sub Total (2026) |
107.08 |
|
||||
2028 |
||||||
4 |
Siachen Energy Ltd |
Muhammad Sohail Shamsi |
Taluka Mirpur Sakro, Dist.Thatta, Sindh |
Solar |
100 |
Jun-28 Tariff determination is awaited from NEPRA. |
5 |
Western Energy (Private) Limited |
Tapal Family |
Jhimpir, District Thatta, Sindh |
Wind |
50 |
Jun-28 Tariff determination is awaited from NEPRA |
6 |
Transatlantic Energy Private Limited |
Waqas A Qureshi, Pervaiz Qureshi, Ali Muskatiya, Shahreyar Nawabi, Burkat A Qureshi |
Jhimpir, District Thatta, Sindh |
Wind |
50 |
Jun-28 Tariff determination is awaited from NEPRA |
7 |
Oracle Power Project |
Oracle Coal Fields PLC England |
Thar Block VI, Sindh |
Thar Coal |
1,320 |
Dec-28 Project Proposal is Under Review. |
Sub Total (2028) |
1,520 |
|
||||
2029 |
||||||
8 |
Turtonas-Uzghor |
Sinohydro-Sachal Consortium |
Golen Gol River, Chitral Valley KP |
Hydel |
82.25 |
Dec-29 LOI issued. FS completed and approved by POE. |
9 |
300 MW coal based Power Project |
CIHC Pak Power Co. Ltd |
Gwadar, Balochistan |
Imported Coal |
300 |
Dec-29
LOS issued
|
Sub Total (2029) |
382.25 |
|
||||
2033 |
||||||
10 |
Azad Pattan |
Azad Pattan Power (Pvt) Ltd. |
Jehlum River, Sudhnoti, AJ&K |
Hydel |
700.7 |
Sep-33 LOS issued
|
11 |
Mahl |
Mahl Power Co. (Pvt) Ltd. |
Jehlum River, AJ&K/ Punjab |
Hydel |
640 |
Dec-33 LOI issued. FS completed and approved by POE. Tariff determined by NEPRA. |
Sub Total (2033) |
1,340.7 |
|
||||
2034 |
||||||
12 |
Kohala |
Kohala Hydro Co. (Pvt) Ltd. |
Jehlum River/ Barsala, AJ&K |
Hydel |
1,124 |
Mar-34 LOS issued
|
Sub Total (2034) |
1,124 |
|
||||
Other Projects |
||||||
13 |
Athmuqam |
Korea Hydro and Nuclear Power Co. |
Neelum River, AJ&K |
Hydel |
450 |
LOI issued. FS completed and approved by POE. |
14 |
Ashkot |
Ashkot Energy (Pvt) Ltd. |
Neelum River, AJ&K |
Hydel |
300 |
Project has been transferred by GoAJ&K to PPIB for further processing |
15 |
Rajdhani |
- |
Poonch River AJ&K |
Hydel |
132 |
- |
16 |
Kaigah |
- |
Kaigah, Indus River, KP |
Hydel |
548 |
|
17 |
Chakothi-Hattian |
- |
Muzaffarabad, AJ&K |
Hydel |
500 |
|
18 |
Neckeherdim-Paur |
- |
Yarkun River, Chitral Valley KP |
Hydel |
80 |
|
19 |
Hatim Power Project |
Pakistan Petroleum Ltd. |
Near Shahdadpur, District Sangarh, Sindh |
Low BTU Gas |
20 |
|
Sub Total (Other Projects) |
2,030 |
|
||||
Grand Total |
6,536 |
|
Note: Under construction projects would be completed by April 2025 & December 2026. Remaining projects will be processed and their exact dates for commissioning will be finalized subject to their inclusion in the Indicative Generation Capacity Expansion Plan (IGCEP) on least cost basis and resolution of various issues.
COD = Commercial Operation Date, FC = Financial Close, LOS = Letter of Support, LOI = Letter of Intent/Interest, FS = Feasibility Study, POE = Panel of Experts, IGCEP = Indicative Generation Capacity Expansion Plan, HPP = Hydropower Project