Portfolio of Upcoming Power Generation Projects

As on September 15, 2024

Sr.# Project Sponsor/ Company Name Location Fuel    Capacity
(MW)
Expected COD/Remarks
2024
1* Shah Taj Sugar Mills Project Shah Taj Sugar Mills Mandi Baha-ud-Din, Punjab Bagasse 32 Dec-24 (Under Construction)
Sub Total (2024) 32
2025
2 Zorlu Solar Pakistan Ltd Zorlu Enerji, Turkiye QASP, Bahawalpur, Punjab Solar 100 Oct- 25 TLOS issued. FC in Progress
3 Tay Powergen Company (Private) Limited Tay Powergen Company (Private) Limited Tando Allahyar, Sindh Bagasse 30 Dec-25 Cat-I Project.
4 300 MW coal based Power Project CIHC Pak Power Co. Ltd  Gwadar, Balochistan Imported Coal 300  Dec-25 LOS issued FC in progress
5 Safe Solar Pakistan (Pvt) Ltd Safe Solar Bahawalnagar, Punjab Solar 10.27 LOS issued Slow Progress
Sub Total (2025) 440.27
2026
6 Access Solar (Pvt) Ltd Tech Access FZLL Pind Dadan Khan, Jhelum, Punjab Solar 11.52 Apr-26 LOS Issued FC in progress
7 Access Electric (Pvt) Ltd Tech Access FZLL Pind Dadan Khan, Jhelum, Punjab Solar 10 Apr-26 LOS Issued FC in progress
8 Riali-II HPP Riali Hydro Power Co. Ghori Wala Nullah, Muzaffarabad AJ&K Hydel 7.08 Dec-26 LOS issued Under FC / under Construction
Sub Total (2026) 28.60
2027
9 Kathai-II HPP Kathai-II Hydro (Pvt) Ltd. Kathai Nullah, Hattian, AJ&K Hydel 8.00 Dec-27 LOS issued FC in Progress
Sub Total (2027) 8.00
2028
10 Siachen Energy Ltd Muhammad Sohail Shamsi Taluka Mirpur Sakro, Dist.Thatta, Sindh Solar 100 Jun-28 Tariff determination is awaited from NEPRA.
11 Western Energy (Private) Limited Tapal Family Jhimpir, District Thatta, Sindh Wind 50 Jun-28 Tariff determination is awaited from NEPRA
12 Transatlantic Energy Private Limited Waqas A Qureshi, Pervaiz Qureshi, Ali Muskatiya, Shahreyar Nawabi, Burkat A Qureshi Jhimpir, District Thatta, Sindh Wind 50 Jun-28 Tariff determination is awaited from NEPRA
13 Oracle Power Project Oracle Coal Fields PLC England Thar Block VI, Sindh Thar Coal 1,320 Dec-28 Project Proposal is Under Review.
Sub Total (2028) 1,520
2029
14 Turtonas-Uzghor HPP Sinohydro-Sachal Consortium Golen Gol River, Chitral Valley KP Hydel 82.25 Dec-29 LOI issued. FS completed and approved by POE.
Sub Total (2029) 82.25
2031
15 Ashkot HPP Ashkot Energy (Pvt) Ltd. Neelum River, AJ&K Hydel 300 Sep-31 Project has been transferred by GoAJ&K to PPIB for further processing
16 Rajdhani HPP - Poonch River AJ&K Hydel 132 Dec-31 To be processed as per the requirements of new capacity in the IGCEP
Sub Total (2031) 432
2032
17 Azad Pattan HPP Azad Pattan Power (Pvt) Ltd. Jehlum River, Sudhnoti, AJ&K Hydel 700.7 Sep-32 LOS issued FC in progress
18 Mahl HPP CWE Investment Corporation/ China Three Gorges & Trans Tech Pakistan Jehlum River, AJ&K/ Punjab Hydel 640 Dec-32 LOI issued. FS completed and approved by POE. Tariff determined by NEPRA.
Sub Total (2032) 1,340.7
2034
19 Kohala HPP Kohala Hydro Company Limited Jehlum River/ Kohala, AJ&K Hydel 1,124  Mar-34 LOS issued FC in progress
Sub Total (2034) 1,124
Other Projects
20 Athmuqam HPP Korea Hydro and Nuclear Company Neelum River, AJ&K Hydel 450 LOI issued. FS completed and approved by POE.
21 Kaigah HPP Project - Kaigah, Indus River, KP Hydel 548 To be processed as per the requirements of new capacity in the IGCEP
22 Chakothi-Hattian HPP - Muzaffarabad, AJ&K Hydel 500
23 Neckeherdim-Paur HPP - Yarkun River, Chitral Valley KP Hydel 80
24 Hatim Power Project Pakistan Petroleum Ltd. Near Shahdadpur, District Sangarh, Sindh Low BTU Gas 20
Sub Total (Other Projects) 1,598
Grand Total 6,605.82

* Under construction project

Note: Under construction project would be completed by end of 2024. For remaining projects, exact date for commissioning will be finalized as per the Indicative Generation Capacity Expansion Plan (IGCEP) which is under approval by NEPRA and subject to the resolution of various issues.

COD = Commercial Operation Date, FC = Financial Close, LOS = Letter of Support, LOI = Letter of Intent/Interest, FS = Feasibility Study, POE = Panel of Experts, IGCEP = Indicative Generation Capacity Expansion Plan, HPP = Hydropower Project