JAPAN POWER PROJECT |
Salient Features |
Company |
Japan Power Generation |
Capacity |
120 MW (Gross) |
Location |
Off Raiwind Road, Near Jia Bagga |
Fuel |
Residual Furnace Oil (RFO) |
Technology |
Diesel Engines |
Plant Configuration |
24 Oil Fired Units |
Power Purchaser |
WAPDA |
Fuel Supplier |
PSO |
Term of the PPA |
30 Years |
Registered Address |
Japan Power Generation Limited Jia Bagga, Raiwind Road Lahore. |
Email |
jpgl@brain.net.pk |
Important Milestones |
Submission of Application |
June 28, 1994 |
Issuance of Letter of Interest (LOI) |
June 29, 1994 |
Issuance of Letter of Support (LOS) |
July 27, 1994 |
Date of Financial Closing |
January 24, 1996 |
Commissioning Date |
March 14, 2000 |
Net / Dependable Capacity |
120 MW |
Contractual Agreements |
Implementation Agreement (IA) |
May 30, 1995 |
Power Purchase Agreement (PPA) |
March 21, 1995 |
Fuel Supply Agreement (FSA) |
February 2, 1995 |
GOP Guarantee |
April 15, 1996 |