ENGRO THAR COAL POWER & MINE PROJECT

Salient Features

Project Company Engro Powergen Thar Limited
Sub Category CPEC
Main Sponsor Engro Powergen Limited
Other Sponsors EPL, HBL, CMEC
Location Thar Block-II Sindh
Technology Steam Turbines
Configration 2 X 330 MW
Total Project Price(USD) 995.4Million
Primary Fuel Thar Coal
Fuel Supplier Sindh Engro Coal Mining Company (SECMC)

Important Events

Submission of Proposal 09-JUN-2014
Approval of PPIB Board 02-JUL-2014
Issuance of Notice to Proceed 31-OCT-2014
Issuance of LOI 20-NOV-2014
Generation License Application 18-MAR-2015
Tariff Determination 13-MAR-2015
Date of issuance of LOS 17-APR-2015
Implementaion Agreement 04-MAY-2015
Direct Implementation Agreement 24-MAR-2016
Power Purchase Agreement 04-MAY-2015
Fuel Supply Agreement 07-JUN-2015
Water Use Agreement 19-NOV-2015
Achievement of Financial Close 04-APR-2016
COD 10-JUL-2019