CPEC Projects (Commissioned & Upcoming)

As on March 13, 2025

Sr. No.

Project Tile

Capacity

(MW)

Location

Project Cost US$ (MILL.)

Current Status

HYDROPOWER

1

Karot

720

River Jhelum, Punjab

1698  

Commissioned on 29-Jun-22

2

Suki Kinari

884

Kagan, River Kunhar, KP

1963

Commissioned on 14-Sep-24

3

Azad Pattan

700

River  Jhelum, AJK

1350

LOS Issued; Expected COD Sep-2033

4

Kohala

1124

River  Jhelum, AJK

2408

LOS Issued; Expected COD Mar-2034

TOTAL HYDEL =

3,428

 

7,419

 

IMPORTED COAL

5

Sahiwal Coal Power Project

1320

Sahiwal, Punjab

1912

Commissioned on 28-Oct-17

6

Port Qasim Coal Power Project

1320

Port Qasim, Sindh

1912

Commissioned on 25- April-18

7

HUBCO Coal Power Project

1320

Hub, Balochistan

1912

Commissioned on 17-Aug-19

8

Gwadar Coal Project

300

Gwadar, Balochistan

444

LOS Issued

Expected COD: Dec-29

TOTAL IMP. COAL =

4,260

 

6,180

 

THAR COAL

9

Engro Thar Coal Power & Mine Project

660

Thar Block-II, Sindh

995

Commissioned on 10-Jul-19

10

HUBCO Thar Coal Power Project (Thar Energy)

330

Thar Block-II, Sindh

498

Commissioned on 1st October 2022

11

ThalNova Thar Coal Power Project

330

Thar Block-II, Sindh

498

Commissioned on 17th February 2023

12

Shanghai Electric (TCB-1)

1320

Thar Block-I, Sindh

1912

Commissioned on 05th February 2023

13

Oracle Coal Project

1320

Thar Block-VI, Sindh

1,912

Project Proposal is Under Review.

Expect COD: Dec-28

TOTAL THAR COAL =

3,960

 

5,815

 

SOLAR

14

Appolo Solar Development Pakistan Ltd. Solar Project

100

Bahawalpur, Punjab

151.4

Commissioned on 31-May-2016

15

Best Green Energy Pakistan Ltd. Solar Project

100

Bahawalpur, Punjab

151.4

Commissioned on 31-Jul-2016

16

Crest Energy Pakistan Ltd. Solar Project

100

Bahawalpur, Punjab

151.4

Commissioned on 31-Jul-2016

17

Zonergy Company Ltd. Solar Power Projects

6 x 100

Bahawalpur, Punjab

414

LOI Stage

TOTAL SOLAR =

900

 

868

 

WIND

18

Hydro China Dawood Wind Farm

50

Gharo, Thatta

122

Commissioned on 5-Apr-2017

19

UEP Wind Farm

100

Jhimpir, Thatta

243

Commissioned on 16-Jun-2017

20

Sachal Wind Farm

50

Jhimpir, Thatta

134

Commissioned on 18-Apr-2017

21

Three Gorges Second Wind Power Project

50

Jhimpir, Thatta

106

Commissioned on 30-Jun-2018

22

Three Gorges Third Wind Power Project

50

Jhimpir, Thatta

106

Commissioned on 09-Jul-2018

23

Cacho Power Project

50

Jhimpir, Thatta

75

LOI Stage

24

Western Energy (Pvt.) Ltd. Project

50

Jhimpir, Thatta

75

LOI Stage

TOTAL WIND =

400

 

861

 

GRAND TOTAL =

12,948

 

21,143

 

TRANSMISSION

1

+660 kV Matiari-Lahore  HVDC Transmission Project

4000

Sindh & Punjab

1658

Commissioned on 1st Sep. 2021

NOTE: Upcoming projects will be processed and their exact dates for commissioning will be finalized subject to their inclusion in the Indicative Generation Capacity Expansion Plan (IGCEP) on least cost basis and resolution of various issues.