CHINA POWER HUB GENERATION COMPANY (PRIVATE) LIMITED |
Salient Features |
Project Company |
China Power Hub Generation Company (Private) Limited |
Main Sponsor |
Hub Power Company Limited |
Other Sponsors |
China Power International Holding |
Location |
Hub, Baluchistan |
Gross Capacity |
1320MW |
Net Capacity |
1214MW |
Technology |
Super-Critical Steam Turbine |
Configration |
2X660 |
Total Project Price(USD) |
1912.2Million |
Power Purchaser |
Central Power Purchasing Agency (Guarantee) Limited |
Primary Fuel |
Imported Coal |
Important Events |
Issuance of LOI |
29-JUN-2015 |
Generation License Application |
26-AUG-2015 |
Tariff Determination |
20-FEB-2016 |
Date of issuance of LOS |
12-APR-2016 |
Implementaion Agreement |
25-JAN-2017 |
Power Purchase Agreement |
25-JAN-2017 |
Achievement of Financial Close |
26-JAN-2018 |
COD |
17-AUG-2019 |