QUAID-E-AZAM THERMAL POWER PROJECT |
Salient Features |
Project Company |
Quaid-e-Azam Thermal Power Ltd. (QATPL) |
Main Sponsor |
Government of Punjab |
Location |
Bhikki, district Sheikhupura, Punjab |
Gross Capacity |
1180.13MW (at RSC) |
Net Capacity |
1156.675MW (at RSC) |
Technology |
Combined Cycle Gas Turbine (GE H Class - 9HA.01 CCGT) (Multi-Shaft) |
Configration |
2GT+2HRSG+1ST |
Total Project Price(USD) |
769.976Million |
Debt Equity Ratio |
75% Debt & 25% Equity |
Power Purchaser |
CPPA-G |
Primary Fuel |
R-LNG |
Secondary Fuel |
HSD |
Fuel Supplier |
SNGPL |
Net Efficiency |
61.59% |
Important Events |
Submission of Proposal |
24-JUN-2015 |
Approval of PPIB Board |
14-MAR-2016 |
Issuance of Notice to Proceed |
06-JUL-2015 |
Issuance of LOI |
13-JUL-2015 |
Generation License Application |
15-JUL-2016 |
Tariff Determination |
14-APR-2016 |
Date of issuance of LOS |
09-MAY-2016 |
Implementaion Agreement |
16-AUG-2016 |
Power Purchase Agreement |
22-JUL-2016 |
Fuel Supply Agreement |
22-JUL-2016 |
Achievement of Financial Close |
22-AUG-2016 |
Partial Commissioning 1 |
17-JUN-2017 GT-1 Commissioning |
Partial Commissioning 2 |
08-MAY-2017 GT-2 Commissioning |
COD |
20-May-2018 |