Hub Power Project |
Salient Features |
Company |
Hub Power Company |
Capacity |
1292 MW (Gross) |
Location |
Tehsil Hub, District Lasbela, Balochistan |
Fuel |
Residual Furnace Oil (RFO) |
Technology |
Oil Fired, Steam Turbines |
Plant Configuration |
4x323 MW Steam Turbines |
Power Purchaser |
WAPDA |
Fuel Supplier |
PSO |
Term of the PPA |
30 Years |
Registered Address |
Hub Power Company Limited Islamic Chamber Building Block-9, Clifton Karachi. |
Email |
info@hubpower.com |
Important Milestones |
Submission of Application |
January, 1988 |
Issuance of Letter of Interest (LOI) |
April 27, 1994 |
Issuance of Letter of Support (LOS) |
None |
Date of Financial Closing |
January 26, 1995 |
Commissioning Date |
March 31, 1997 |
Net / Dependable Capacity |
1200 MW |
Contractual Agreements |
Implementation Agreement (IA) |
August 3, 1992 |
Power Purchase Agreement (PPA) |
August 3, 1992 |
Gas Supply Agreement (GSA) |
August 3, 1992 |
GOP Guarantee |
January 3, 1995 |
Settlement Agreement |
December 17, 2000 |
Settlement Amended Agreement |
October 14, 2001 |