RLNG BASED IPP PROJECT AT HAVELI BAHADUR SHAH

Salient Features

Project Company National Power Parks Management Company (Pvt) Ltd (NPPMCL), MoW&P
Main Sponsor MoW&P, GoP
Location Haveli Bahadur Shah, district Jhang, Punjab
Gross Capacity 1230.542MW
Technology Comibined Cycle Gas Turbine (GE H Class - 9HA.01 CCGT) (Multi-shaft)
Configration 2GT-2HRSG+1ST
Total Project Price(USD) 853.774Million
Power Purchaser CPPA-G
Primary Fuel R-LNG
Secondary Fuel HSD
Fuel Supplier SNGPL
Net Efficiency 62.445%

Important Events

Submission of Proposal 25-FEB-2016
Approval of PPIB Board 14-MAR-2016
Issuance of Notice to Proceed 15-MAR-2016
PG Validity 24-SEP-2016
Issuance of LOI 12-APR-2016
Generation License Application 21-APR-2016
Tariff Determination 09-AUG-2016
Date of issuance of LOS 22-SEP-2016
Implementaion Agreement 14-NOV-2016
Power Purchase Agreement 29-OCT-2016
Fuel Supply Agreement 29-OCT-2016
EPC Contract 13-OCT-2015
Achievement of Financial Close 28-NOV-216
Partial Commissioning 1 18-JUL-2017
Partial Commissioning 2 18-JUL-2017
COD 09-May-2018