FAUJI KABIRWALA POWER PROJECT

Salient Features

Company Fauji Kabirwala Power Company Limited
Capacity 157 MW (Gross)
Location Kabirwala, District Khanewal
Fuel Low BTU Gas + Pipeline Quality Gas
Technology Combined Cycle + Steam Turbines
Plant Configuration 2 Gas Turbines of 48.4 MW each and a Steam Turbine of capacity 59.4 MW
Power Purchaser WAPDA
Fuel Supplier OGDC
Term of the PPA 30 Years
Registered Address Fauji Kabirwala Power Co. Ltd. 14 Harley Street Rawalpindi Cantt
Email fkpcl567@comsats.net.pk

Important Milestones

Submission of Application April 28, 1994
Issuance of Letter of Interest (LOI) May 19, 1994
Issuance of Letter of Support (LOS) June 30, 1994
Date of Financial Closing June 2, 1996
Commissioning Date October 21, 1999
Net / Dependable Capacity 151 MW

Contractual Agreements

Implementation Agreement September 24, 1994
Amendment No. 1 January 28, 1996
Power Purchase Agreement (PPA) January 12, 1995
Amendment No. 1 January 25, 1996
GOP Guarantee July 23, 1996