RLNG BASED BALLOKI

Salient Features

Project Company National Power Parks Management Company (Pvt.) Ltd. (NPPMCL), Mo Energy
Main Sponsor Mo Energy (Power Division) GoP
Location Balloki, district Kasur, Punjab
Gross Capacity 1223.10MW (at RSC)
Net Capacity 1198.56MW (at RSC)
Technology Combined Cycle Gas Turbine
Configration 2GT + 2HRSG + 1 ST
Total Project Price(USD) 798.183Million
Debt Equity Ratio 70 :30
Power Purchaser CPPA-G
Primary Fuel R-LNG
Fuel Supplier SNGPL
Net Efficiency 61.63%

Important Events

Submission of Proposal 25-Feb-2016
Approval of PPIB Board 14-Mar-2016
Issuance of Notice to Proceed 15-Mar-2016
Issuance of LOI 12-Apr-2016
Generation License Application 21-Apr-2016
Tariff Determination 9-Aug-2016
Date of issuance of LOS 22-Sep-2016
Implementaion Agreement 14-NOV-2016
Power Purchase Agreement 29-OCT-2016
Fuel Supply Agreement 29-OCT-2016
Achievement of Financial Close 28-NOV-2016
Partial Commissioning 1 13-Aug-2017
Partial Commissioning 2 30-AUG-2017
COD 29-JUL-2018