RLNG BASED BALLOKI |
Salient Features |
Project Company |
National Power Parks Management Company (Pvt.) Ltd. (NPPMCL), Mo Energy |
Main Sponsor |
Mo Energy (Power Division) GoP |
Location |
Balloki, district Kasur, Punjab |
Gross Capacity |
1223.10MW (at RSC) |
Net Capacity |
1198.56MW (at RSC) |
Technology |
Combined Cycle Gas Turbine |
Configration |
2GT + 2HRSG + 1 ST |
Total Project Price(USD) |
798.183Million |
Debt Equity Ratio |
70 :30 |
Power Purchaser |
CPPA-G |
Primary Fuel |
R-LNG |
Fuel Supplier |
SNGPL |
Net Efficiency |
61.63% |
Important Events |
Submission of Proposal |
25-Feb-2016 |
Approval of PPIB Board |
14-Mar-2016 |
Issuance of Notice to Proceed |
15-Mar-2016 |
Issuance of LOI |
12-Apr-2016 |
Generation License Application |
21-Apr-2016 |
Tariff Determination |
9-Aug-2016 |
Date of issuance of LOS |
22-Sep-2016 |
Implementaion Agreement |
14-NOV-2016 |
Power Purchase Agreement |
29-OCT-2016 |
Fuel Supply Agreement |
29-OCT-2016 |
Achievement of Financial Close |
28-NOV-2016 |
Partial Commissioning 1 |
13-Aug-2017 |
Partial Commissioning 2 |
30-AUG-2017 |
COD |
29-JUL-2018 |