Sr.

#

Project

Sponsor/

Company Name

Power Policy

Location

Fuel

Capacity 
(MW)

Expected COD/Remarks

2017

1

Patrind Hydropower Project

Star Hydropower Limited

2002

Kunhar River, KP/AJ&K

Hydel

147

Aug-17

 

Under testing & commissioning

2*

1320 MW Imported coal based Power Project at Qadarabad Dist Sahiwal

Huaneng Shandong Ruyi (Pakistan) Energy (Pvt) Limited

2015

Qadarabad, District Sahiwal

Coal

First Unit

660

 

Second Unit

660

Inaugurated on 25.05.17

 

Inaugurated on 03.07.17

3(i)*

1320 MW Imported coal based Power Project

Port Qasim Electric Power Co. (Pvt) Ltd

2015

Port Qasim, Karachi

Coal

First Unit

660 MW

Dec-17

 

 

Under construction

4

1180 MW RLNG based Project at Bhikki

QATPL

2015

Bhikki, Punajb

RLNG

1180

Open Cycle (717 MW) commissioned 

 

Combined Cycle by Dec-17

5(i)

1223 MW RLNG based Project at Balloki, Punjab

NPPMCL

2015

Balloki, Punjab

RLNG

GT1 & GT2

800

Open Cycle by

Sep-17

6(i)

1230 MW RLNG based Project at Haveli Bahadur Shah, Punjab

NPPMCL

2015

Haveli Bahadur Shah, Punjab

RLNG

GT1 & GT2

800

Open Cycle (760 MW) inaugurated on 07.07.17  

7

Fatima Energy Cogeneration Project

Fatima Energy Limited

Co-gen Policy 2008

Muzaffargarh

Bagasse/ Imported Coal

118

Dec-17

 

LOS issued

FC in progress

(Under Construction)

Sub Total (2017)

5025

 

2018

5(ii)

1223 ME RLNG based Project at Balloki, Punjab

NPPMCL

2015

Balloki, Punjab

RLNG

ST

423

Combined Cycle by Jan-18

6(ii)

1230 MW RLNG based Project at Haveli Bahadur Shah, Punjab

NPPMCL

2015

Haveli Bahadur Shah, Punjab

RLNG

ST

430

Combined Cycle by Jan-18

8(i)*

 

1320 MW Imported coal based Power Project at HUB Balochistan

China Power HUB Generation Co. Ltd.  

2015

HUB, Balochistan

Coal

 

 

First Unit

660 MW

 

Dec-18

 

LOS issued

FC in progress

(under construction)

9(i)*

660 MW Thar Coal based Power Project

Engro Powergen Thar Limited

2015

Thar

Block-II, Sindh

Coal

 

First Unit

330 MW

Dec-18

 

FC achieved

Under construction

3(ii)*

1320 MW Imported coal based Power Project

Port Qasim Electric Power Co. (Pvt) Ltd

2015

Port Qasim, Karachi

Coal

Second Unit

660 MW

Jun-18

 

FC achieved.

Under construction

Sub Total (2018)

2503

 

2019

10

163MW imported coal based Power Project at Arifwala Punjab

Grange Power Limited

2002

Arifwala, Punjab

Coal

163

Jan-19

 

LOS issued

FC in progress

8(ii)*

 

1320 MW Imported coal based Power Project at HUB Balochistan

China Power HUB Generation Co. Ltd.  

2015

HUB, Balochistan

Coal

 

Second Unit

660 MW

 

 

Aug-19

 

 

11

Gulpur Hydropower project

Mira Power Ltd

2002

Poonch River/Gulpur, AJ&K

Hydel

102

Oct-19

 

FC achieved

Under Construction

9(ii)*

660 MW Thar Coal based Power Project

Engro Powergen Thar Limited

2015

Thar

Block-II, Sindh

Coal

 

Second Unit

330 MW

 

Jun-19

 

Sub Total (2019)

1255

 

2020

12*

1320 MW Thar Coal based Power Project

Thar Coal Block-I Power Generation Co. Ltd.

2015

Thar

Block-I, Sindh

Coal

1320

Jun-20

 

LOS issued

FC in progress

13*

330 MW Thar Coal based Power Project

Thar Energy Limited

2015

Thar Block-II, Sindh

Coal

330

Dec-2020

 

LOS issued

FC in Progress

(under construction)

14*

330 MW Thar Coal based Power Project

Thal Nova Power Thar (Pvt) Ltd

2015

Thar Block-II,

Sindh

Coal

330

Dec-2020

 

LOS issued

FC in Progress

Sub Total (2020)

1980

 

2021 

15

660 MW Thar Coal based Power Project

Lucky Electric Power Company Ltd.

2015

Port Qasim, Karachi

Coal

660

Jun-21

 

LOS issued

FC in progress

16

330 MW Thar Coal based Power Project

Siddiqsons Energy Limited

2015

Thar Block-II

Coal

330

Sep-21

 

LOS issued

FC in progress

17*

1320MW Thar coal based Power Project

Oracle Coal Fields PLC England

2015

Thar Block VI, Sindh

Coal

1320

2nd quarter of 2021

 

Project proposal yet to be submitted

18*

300 MW Imported coal based Power Project at Gawadar

China Communication Construction Co. Ltd. (CCCC)

2015

Gawadar

Coal

300

Dec-21

 

LOI issued

19*

Karot Hydropower Project

Karot Power Company Pvt Ltd

2002

Jehlum River, Distt. Rawalpindi

Punjab

Hydel

720

Dec-21

 

FC achieved

Under construction

Sub Total (2021)

3330

 

2022

20*

Suki Kinari Hydropower Project 

S.K Hydro Pvt Ltd

2002

Kunhar River/Mansehra, KP

Hydel

870

Dec-22

 

FC achieved

Under construction

Sub Total (2022)

870

 

2024

21*

Kohala Hydropower Project

China International Water & Electric Company

2002

Jehlum River/Kohala, AJ&K

Hydel

1124

Jun-24

 

LOS issued

FC in progress

22

Chakothi-Hattian Hydropower Project

Suhail Jute Mills Ltd

2002

Muzaffarabad, AJ&K

Hydel

500

Jun-24

 

Feasibility Study level tariff determined by NEPRA. PPIB has requested the Sponsors for submission of Performance Guarantee for issuance of LOS.

23

Azad Pattan Hydropower Project

Alamgir Power Pvt Ltd

2002

Jehlum River/Sudhnoti, AJ&K

Hydel

640

Dec-24

 

LOS issued

FC in progress

24

Kaigah Hydropower Project

Telecom Valley Pvt Ltd

2002

Kaigah/Indus River, KP

Hydel

548

Dec-24

 

Feasibility Study completed. Sponsors submitted feasibility study level tariff to NEPRA

Sub Total (2024)

2812

 

2025

25

Mahl Hydropower Project

 

CWE Investment Corporation/ China Three Gorges & Trans Tech Pakistan

2002

Jehlum River, AJ&K/Punjab

Hydel

590

Dec-25

 

LOI issued.

FS completed and approved by POE. Tariff Application has been filed with CPPAG for negotiation

26

Turtonas-Uzghor Hydropower Project

Sinohydro-Sachal Consortium

2015

Golen Gol River, Chitral Valley KP

Hydel

58

Dec-25

 

LOI issued.

Feasibility Study in progress

27

Athmuqam Hydropower Project

Korea Hydro and Nuclear Company

 

2015

Neelum River, AJ&K

Hydel

350

Dec-25

 

LOI issued.

Feasibility Study in progress

Sub Total (2025)

998

 

28

Rajdhani Hydropower Project

-

2002

Poonch River AJ&K

Hydel

132

COD will be mentioned after getting consent of GoAJ&K for implementation of this project by PPIB

29

Neckeherdim-Paur Hydropower Project

-

2015

 Yarkun River, Chitral Valley KP

Hydel

80

 

** To be advertised shortly

30

Madian Hydropower  Project

-

2015

Swat River, KP

Hydel

157

** To be advertised shortly

31

Asrit-Kedam Hydropower Project

-

2015

Near Kalam/Swat River, KP

Hydel

215

** To be advertised shortly

32

Kalam-Asrit Hydropower Project

-

2015

Swat River, KP

Hydel

197

** To be advertised shortly

Sub Total

781

 

Grand Total

19554

 

 
TRANSMISSION LINE PROJECT

Sr.

#

Project

Sponsor/

Company Name

Transmission Line Policy

Location

Technology

Expected COD/Remarks

1*

Matiari-Lahore HVDC Transmission Line Project

China Electric Power Equipment and Technology Co. Ltd. (CET)/ State Grid Corporation of China (SGCC)

TLP 2015

Matiari to Lahore

(Approx 880 Km)

+ 660 kV HVDC Transmission Line

 

2020

 

LOS issued.

 

Tariff Approved by NEPRA

FC in progress

*    CPEC Projects

** COD will be assessed after issuance of LOI

GT = Gas Turbine

ST = Steam Turbine

 Home  Links Tenders   Careers