PRIVATE POWER & INFRASTRUCTURE BOARD

 

GOVERNMENT OF PAKISTAN

MINISTRY OF ENERGY (Power Division)

   
  SAHIWAL COAL POWER PROJECT

 

Salient Features

Company

Huaneng Shandong Ruyi (Pak) Energy (Pvt) Ltd

Capacity

1320 MW (Gross)

Location

Qadarabad, Sahiwal

Fuel

Imported Coal

Technology         

Super-Critical Steam Turbine

Plant Configuration

2x660

Power Purchaser           

Central Power Purchasing Agency (Guarantee) Limited

Term of the Project 30 Years
Registered Address HNo 105, Street 10, Block H, Phase 5, DHA Lahore

Email

huanengruy_energy@163.com

Important Milestones

LOI by Punjab Power Development Board:

21st May 2014

Approval of EIA by PEPA:

28th May 2014

Approval of application for acceptance of Upfront Tariff by NEPRA:

31st March 2015

Tripartite LOS by PPIB & PPDB:

17th April 2015

Generation License by NEPRA:

10th June 2015

Implementation Agreement:

11th July 2015

Power Purchase Agreement:

11th July 2015

Supplemental Agreement to Implementation Agreement:

4th February 2016

Financial Closing:

23rd January 2017

First Unit Inauguration:

25th May 2017

Second Unit Inauguration:

3rd July 2017

Commercial Operations Date:

28th October 2017

 
 
 
     
 