PRIVATE POWER & INFRASTRUCTURE BOARD

 

GOVERNMENT OF PAKISTAN

MINISTRY OF WATER & POWER

   
  ROUSCH POWER PROJECT

 

Salient Features

Company

Rousch (Pakistan) Power Limited

Capacity

412 MW (Gross)

Location

Abdul Hakeem (Near Sidhnai Barrage), District Khanewal (about 85 KM North-East of Multan)

Fuel

Residual Fuel Oil (RFO)

Technology

Combined Cycle

Plant Configuration

Two Gas Turbines + One Steam Turbine

Power Purchaser

WAPDA

Fuel Supplier

PSO

Term of the PPA 30 Years
Registered Address

Rousch (Pakistan) Power Ltd.

39-C/IV, Block-6, P.E.C.H.S.

Karachi.

Email

rousch@rouschpak.com

Important Milestones

Submission of Application

May 10, 1994

Issuance of Letter of Interest (LOI)          

June 22, 1994

Issuance of Letter of Support (LOS)

August 8, 1994

Date of Financial Closing

April 7, 1996

Commissioning Date

December 11, 1999

Net / Dependable Capacity

395 MW

Contractual Agreements

Implementation Agreement (IA)

June 15, 1995

Amended and Restated

March 31, 1996

Power Purchase Agreement (PPA) 

February 25, 1996

Amendment No. 1

May 25, 1996

Amendment No. 2

July 7, 1996

Fuel Supply Agreement (FSA)

July 23, 1995

GOP Guarantee

August 2, 1996

     
 
 
 
     
 