PRIVATE POWER & INFRASTRUCTURE BOARD

 

GOVERNMENT OF PAKISTAN

MINISTRY OF Energy(Power Division)

   
  PATRIND HYDROPOWER PROJECT

 

Salient Features

Company

Star Hydropower Limited

Capacity

147 MW (Gross)

Location

Muzaffarabad AJK

Fuel

Hydro 

Technology         

Hydro 

Configuration

50 MW x 3 Francis Turbines.  

Power Purchaser           

CPPAG (NTDCL)  

Term of Project 30 Years 
Registered Address Usman Square 3rd & 4th Floor, Main Double Road E-11/2, Islamabad 

Email

patrind@patrind.com 

Important Milestones

Issuance of Letter of Interest (LOI)          

26th October 2005

Issuance of Letter of Support (LOS)

30th June 2010

Date of Financial Closing

20th December 2012

Commissioning Date

8th November 2017

Contractual Agreements

Implementation Agreement (IA)

February 11, 2012

Power Purchase Agreement (PPA) 

March 8, 2012

WUA (AJK)

Feb. 11, 2012

 WUA (KPK)   Oct. 31, 2011 
 
 
 
     
 
 Home  Links Tenders   Careers