  FAUJI KABIRWALA POWER PROJECT

 

Salient Features

Company

Fauji Kabirwala Power Company

Limited

Capacity

157 MW (Gross)

Location

Kabirwala, District Khanewal

Fuel

Low BTU Gas + Pipeline Quality Gas

Technology

Combined Cycle + Steam Turbines

Plant Configuration

2 Gas Turbines of 48.4 MW each and a Steam Turbine of capacity 59.4 MW

Power Purchaser

WAPDA

Fuel Supplier

OGDC

Term of the PPA 30 Years
Registered Address

Fauji Kabirwala Power Co. Ltd.

14 Harley Street

Rawalpindi Cantt

Email

fkpcl567@comsats.net.pk

Important Milestones

Submission of Application

April 28, 1994

Issuance of Letter of Interest (LOI)          

May 19, 1994

Issuance of Letter of Support (LOS)

June 30, 1994

Date of Financial Closing

June 2, 1996

Commissioning Date

October 21, 1999

Net / Dependable Capacity

151 MW

Contractual Agreements

Implementation Agreement

September 24, 1994

Amendment No. 1

January 28, 1996

Power Purchase Agreement (PPA)             

January 12, 1995

Amendment No. 1

January 25, 1996

GOP Guarantee

July 23, 1996

 
 
     
 