PRIVATE POWER & INFRASTRUCTURE BOARD

 

GOVERNMENT OF PAKISTAN

MINISTRY OF ENERGY (POWER DIVISION)

   
  DAVIS ENERGEN POWER PROJECT

 

Salient Features

Photo

Company

Davis Energen Power Limited

Capacity

10 MW (Gross)

Location

Toba Tek Singh District Jhang

Fuel

Gas

Technology

Combined Cycle

Plant Configuration

Three(3) GE Jenbacher gas engines

Power Purchaser           

NTDC/WAPDA

Fuel Supplier

SNGPL
Term of the PPA 30 Years
Registered Address 6-A, Block-H Ancillary Building Gulber Heights, Gulberg-II Lahore
 

Email

 

Important Milestones

Submission of Application

10 May 1994

Issuance of Letter of Interest (LOI)

19 May 1994

Issuance of Letter of Support (LOS)

17 July 1994

Date of Financial Closing

08 Sep 2010

Commissioning Date

13 Jul 2013

Net / Dependable Capacity

10.5 MW

Contractual Agreements

Implementation Agreement (IA)

06 Jun 1995

Amendment to IA

09 April 2010

Power Purchase Agreement (PPA) 

18 Jan 1995

Gas Supply Agreement (GSA)

19 Oct 2006

Amendment in the GSA

Oct 2008

Withdrawal Agreement

-

Memorandum of Understanding

-

GOP Guarantee

-
     
 
 
 
     
 