  NEW BONG ESCAPE HYDROPOWER PROJECT

 

The 1st Hydropower IPP of Pakistan/AJK

Salient Features

Company

Laraib Energy Limited

Capacity

84 MW (Gross)

Location

7Km Downstream Mangla Dam, AJK

River

Jhelum

Project Type

Run of River

Energy

470 Gwh

Term of the PPA

 25 Years

Registered Address

12-B/1, G-8 Markaz, Islamabad

Email

mail@laraibenergy.com

 

 

Important Milestones

Issuance of Letter of Support (LOS) by GOAJK

18th May 1996, valid until 2nd Dec. 2009

Signing of Amended & Restated GOPIA          

31st August 2007

Signing of EPC contract

19th June 2009

Signing of Amended & Restated PPA

22nd October 2009

Signing of Amended & Restated AJKIA

27th October 2009

Signing of AJKIA-DA, WUA-DA, GOPIA-DA

10th November 2009

Signing of PPA-DA

20th November 2009

Signing of Amended & Restated WUA

27th October  2009

Signing of Finance Documents

05th November 2009

Financial Close

  December 2009

COD

23rd March 2013

 

 
 
     
 